Works to reinforce a seafront have started after it was battered by winter storms.
In May, the Environment Agency (EA) announced it had approved £19.8 million for the multi-million pound scheme at Torcross in Devon.
The defences were damaged by multiple storms in January, eventually leading to part of the A379 coastal road between Torcross and Slapton being washed away in February. The road remains closed.
The EA said: "We recognise how important access at the southern end of Torcross beach is to the community, and we are continuing to work on a solution."
Under the plans, the armour, made up of large rocks, will be placed on the beach between the access steps at the southern end and the slipway at the north end.
The Tank carpark in the village has closed to become the compound for the works, with the first rocks arriving on 17 October.
Businesses in Torcross have thanked visitors for their custom over the summer.
Emma Wilson, manager of Start Bay Inn, said takeaways had done particularly well, explaining "we were up on our normal figures for this time of year".
Traffic has been diverted onto inland routes since part of the A379 disappeared. Wilson said she felt this had affected footfall from the Dartmouth area.
"It takes 50 minutes and it's always going to be an issue if they don't fix the road," she said.
She added: "The customers we have had have been brilliant and I hope they keep it up when we need them the most over the winter."
Bridget Myers, visiting from Stoke Fleming, said: "We had to come the long way through Kingsbridge but we want to give our full support to local businesses."
Paul and Beverly Johnson, from Derby, stayed in Dartmouth and visited Torcross as they "love the area" and said they were "very glad" they went.
More news stories for Devon
Listen to the latest news for Devon
Natalie Cordrey, who runs a yoga business Start Bay Studio in the village, said: "Initially when we were given the £19.8m there was a lot of celebration [but] as time has gone on there is some trepidation about the amount of work and the amount of rocks we're going to have, and grieving about losing our beach."
Shingle from Torcross was removed as a result of the storms.
The EA said beach levels at the site "naturally fluctuate".
In a report, published in June,, external it said: "Detailed work over many years by the University of Plymouth show that (in broad terms) whilst southerly winds remove shingle from the Torcross end of Slapton Sands, easterly winds bring it back."
It also explained: "It may be that the natural processes will at times result in shingle partially or fully covering the rock armour."

First Stage of Torcross Seafront Repairs Begins